Greenfield platform extension project

Status | Project is out to bid

This page provides an overview of a project that is now underway to extended the high-level station platform in Greenfield, Massachusetts.

The extension of the platform will allow for simultaneous level access boarding/disembarking of three passenger cars (one door each of the lead and rear cars / both doors of the middle car).

This project is scheduled to be substantially complete by the end of December 2018 with final completion of plantings and other punch list items by May 15, 2019.

 

In summary, the project includes the following components:

  • the high-level platform will be extended from its current length of 46 feet to a a length of 146 feet
  • the canopies will be extended to cover the entire length of the expanded platform
  • new ramps and stairs will be constructed to access the platform extensions
  • Existing ramps, stairs, handrails and guard fence will be modified where required to coordinate with the new construction
  • Closed-circuit video cameras will be added along with station wayfinding signage

 


Selected drawings

Proposed Site Plan | Greenfield station
Elevation / Sections | Greenfield station
Elevation / Sections | Greenfield station

 


Project milestones

July 11, 2018 | The Massachusetts Bay Transportation Authority (for MassDOT) formally advertised MBTA Contract No. T92CN02 – the Knowledge Corridor Northampton and Greenfield Station Platform Extension Project.

August 9, 2018 | Planned date that bids for this project will be opened.

 

Further details to follow.

 


See also

Northampton station platform extension | Trains In The Valley

 


External links

Northampton and Greenfield Platform Extensions | MBTA

 

Page last updated: August 9, 2018
Page last reviewed July 17, 2018